Ad

How to Calculate Printing Cost per Meter – Profit Analysis Guide

 

How to Calculate Printing Cost per Meter – Profit Analysis Guide

A Competitive Printing Rate Can Still Make a Loss

A textile printing order may look profitable when the quotation is prepared, but the final result can be very different. Printing paste consumption may exceed the estimate, machine efficiency may fall, rejected fabric may increase and overhead expenses may remain unaccounted for.

The biggest costing mistake is calculating only the direct material cost and treating the remaining expenses as profit.


For a printing mill, the correct approach is to calculate the complete production cost, divide it by the saleable printed metres and then add a suitable profit margin.

This guide explains how to build that calculation using a practical textile printing order.

First, Define What Your Printing Rate Includes

Before calculating cost per metre, establish the scope of the order. Two printing quotations may look similar but include different services.

Costing scope

What it covers

Printing service only

Printing paste, labour, machine operation, energy and related overhead

Printing with finishing

Printing plus drying, curing, washing or other required finishing

Complete fabric supply

Printing-related costs plus the base fabric and any included processing

This article focuses on printing and its associated production costs, excluding the purchase cost of the base fabric. If the mill supplies the fabric as well, its cost must be added separately.

Another important factor is fabric width. A metre of 1.80 m wide fabric contains more printed area than a metre of 1.50 m wide fabric. For accurate comparison, record both linear metres and usable width.

Build the Cost Sheet: Every Taka Needs a Place

A reliable printing cost sheet should separate direct production expenses from indirect operating expenses.

Direct production costs

These expenses are directly related to the printing order.

Cost component

What to include

Printing paste or ink

Actual consumption multiplied by purchase rate

Printing chemicals

Thickener, binder, auxiliaries and other required chemicals

Labour

Operators and production workers assigned to the order

Energy

Electricity, steam, drying and curing energy

Setup

Design preparation, screen preparation and machine setup where applicable

Indirect production costs

These expenses support the operation but may not belong to one individual metre of fabric.

  • Machine depreciation and maintenance.
  • Factory rent and production overhead.
  • Quality inspection and testing.
  • Production planning and supervision.
  • Cleaning, handling and other operating expenses.

These costs should be allocated using a consistent method, such as productive machine hours or production volume. Avoid counting the same expense twice.

The Core Formula

Printing Cost per Metre = Total Printing Production Cost ÷ Saleable Printed Metres

The important word is saleable. If 10,000 metres enter production but only 9,500 metres pass inspection, the cost must be recovered from the 9,500 saleable metres.

For a more detailed costing sheet:

Total Printing Cost = Material + Labour + Energy + Setup + Machine Cost + Allocated Overhead + Other Production Expenses

This calculation gives the manufacturing cost before adding the desired profit.

Worked Example: Costing a 10,000-Metre Printing Order

Consider a hypothetical rotary screen printing order. The factory processes 10,000 metres, but after inspection, 9,500 metres are accepted for delivery.

The following figures are illustrative and do not represent standard market rates.

Cost component

Order cost (BDT)

Printing paste

180,000

Other printing chemicals

45,000

Labour

80,000

Electricity and steam

65,000

Machine maintenance and depreciation

55,000

Screen and setup cost

40,000

Allocated factory overhead

75,000

Other production expenses

30,000

Total production cost

570,000

Now calculate the actual cost:

Total production cost = BDT 570,000

Saleable printed quantity = 9,500 metres

Printing cost per metre = 570,000 ÷ 9,500

Actual printing cost = BDT 60 per metre

Notice that dividing by the original 10,000 metres would give BDT 57 per metre. That figure understates the true cost of each saleable metre because it ignores the rejected output.

From Production Cost to Selling Price

Knowing the cost per metre is only half the job. The mill must also decide how much profit it wants to earn.

For a target gross profit margin:

Selling Price = Cost per Metre ÷ (1 − Target Gross Margin)

Using the example above, assume the factory targets a 20% gross margin.

Selling price = 60 ÷ (1 − 0.20)

Selling price = BDT 75 per metre

The order's financial result would be:

Financial indicator

Amount

Saleable quantity

9,500 metres

Selling price

BDT 75/metre

Total sales revenue

BDT 712,500

Total production cost

BDT 570,000

Gross profit

BDT 142,500

Gross profit margin

20%

Margin vs Markup: Do Not Confuse Them

This distinction matters when preparing quotations.

  • Markup is profit calculated as a percentage of cost.
  • Gross margin is profit calculated as a percentage of selling revenue.

For example, adding 20% markup to a BDT 60 cost gives a selling price of BDT 72. That produces a gross margin of only 16.67%, not 20%.

A mill targeting a 20% gross margin should therefore use BDT 75 in this example.

Why Two Similar Printing Orders Can Have Different Costs

The printing rate should not be copied blindly from one order to another. Several production factors can change the cost per metre.

Design and colour coverage: A design with greater printed area or more colours may consume more printing paste and require additional preparation.

Printing method: Rotary screen, flat screen and digital printing have different material, setup, machine and operating costs.

Order quantity: Screen preparation and other fixed setup expenses are spread over the order quantity. Smaller orders generally carry a higher setup cost per metre.

Fabric width: Wider fabric increases printed area per linear metre and may change the material consumption and machine-loading calculation.

Production speed: Lower output per hour increases the labour, machine and overhead cost allocated to each metre.

Quality and rejection: Shade variation, print defects and reprocessing reduce saleable output and increase the effective cost.

Where Printing Mills Commonly Lose Profit

Costing weakness

Financial consequence

Better control

Estimating paste consumption

Material cost exceeds budget

Measure actual consumption

Ignoring setup cost

Small orders become underpriced

Allocate setup by order quantity

Using processed metres

Cost per saleable metre looks too low

Use accepted output

Underestimating energy

Operating cost is understated

Track machine-wise consumption

Ignoring reprocessing

Extra expenses remain hidden

Record correction and rejection costs

Applying markup as margin

Selling price misses profit target

Use the correct margin formula

A Simple Costing Control System

A printing mill can improve quotation accuracy by following a consistent costing procedure.

  1. Collect order information: Confirm fabric width, order quantity, design, colours, printing method and required finishing.
  2. Prepare the material estimate: Calculate expected paste, ink and chemical requirements using an approved production trial or reliable historical consumption data.
  3. Estimate machine and labour costs: Use expected production hours, machine rates and labour allocation.
  4. Allocate overhead: Apply the factory's approved overhead method consistently.
  5. Include production losses: Use realistic allowances based on historical rejection and reprocessing records.
  6. Calculate cost per saleable metre: Divide total estimated cost by expected accepted output.
  7. Set the selling price: Apply the required gross margin and check the quotation against commercial conditions.
  8. Compare actual and estimated results: After production, review the cost variance and update future estimates.

Turn the Cost Sheet into a Profit Improvement Tool

A cost sheet should not be prepared only when a new order arrives. It should also help management identify why actual production cost differs from the quotation.

Monitor these indicators regularly:

KPI

Measurement

Printing cost per metre

Total printing cost ÷ saleable metres

Paste consumption

Paste used ÷ printed metres or area

Production efficiency

Actual output ÷ planned output

Rejection rate

Rejected metres ÷ processed metres × 100

Reprocessing rate

Reprocessed metres ÷ processed metres × 100

Energy cost per metre

Printing-related energy cost ÷ saleable metres

Gross profit margin

Gross profit ÷ sales revenue × 100

Compare similar designs, fabric widths and printing methods to make the results meaningful.

The Final Commercial Check

Before confirming a printing quotation, make sure the cost sheet includes all relevant production expenses, the correct saleable quantity, the agreed finishing scope and a realistic profit margin.

A low quotation may win an order, but winning an order is not the same as earning a profit.

The strongest printing cost calculation is one that reflects the real cost of every saleable metre—and protects the mill's profit before production begins.

 

No comments

Thank you for visiting Learn Easy Textile and spending your valuable time reading our articles. We truly appreciate your interest in learning about the textile and apparel industry.

At Learn Easy Textile, our mission is to make textile knowledge simple, clear, and easy to understand for everyone. We share informative articles about textile fibers, yarn, fabric, knitting, weaving, dyeing, printing, finishing, garment manufacturing, fashion trends, merchandising, and the latest developments in the textile industry.

Your comments, feedback, and suggestions are extremely valuable to us. Every opinion helps us improve our content quality and create more useful articles for students, textile professionals, merchandisers, buyers, fashion enthusiasts, and anyone who wants to learn about the textile world.

We encourage our readers to share their thoughts, ask questions, and participate in discussions. If you have any questions about textile processes, garment production, fabric technology, apparel business, or any other textile-related topics, please feel free to leave a comment. We will always try our best to provide helpful information and solutions.

We also welcome suggestions for new article topics. If there is any specific textile subject you would like us to explain, please let us know through your comments or email.

For any queries, suggestions, business inquiries, collaborations, or professional communication, please contact us:

Email: amamun994@gmail.com

Thank you for supporting Learn Easy Textile and being a part of our learning community. Your support motivates us to continue sharing valuable textile knowledge and industry insights.

Stay connected with Learn Easy Textile for more educational articles, practical textile guides, and updates from the world of textiles and garments.

Learn Easy Textile — Making Textile Knowledge Easy to Understand.